#RFs of Bhagalpur,Jamalpur,Munger,Sahibganj and RFs of all over India who take interest in development activies in sahibganj loop i request you to kindy keep an eye and post pics of "Progress of Sub Station at Jamalpur near tunnel, then at bariarpur, then at sultanganj, then at akbarnagar and also keep an eye on electrification of tunnel at Jamalpur". These are key to CRS of Bhagalpur-Kiul Electrification in month of March 19.
#As wiring of whole section from KIUL to Bhagalpur only just an area of 1.5 km remains to come under wire. Wiring is fully completed in all respects till last road crossing at Muslim High School just 300 metres away from bhagalpur jn only station area and eastern...
more... side towards end of yard new poles are getting fixed only area left to comes under wire even one part of wire has reached Bhagalpur jn at platform no 4/5.
#At bhagalpur all poles connecting two platform has been set now with just few poles left to set hookes, work going on at full speed now.
#Only concern is that when will middle fob will be dismantled as wires can't pass through it , this fob is oldest and first fob of bhagalpur jn