RCF Rae Bareli Milestones Of Their Project till date
• Project approved in the supplementary Railway Budget 2006-07.
• Foundation stone laid by the Hon’ble Chairperson, UPA Smt. Sonia Gandhi-13th Feb, 2007
• Land acquisition activities started - 10th Aug, 2007
•...
more... Land lease deed signed with Uttar Pradesh Govt - 16th Jan, 2009
• Inauguration of construction of factory boundary wall by the Hon’ble Chairperson, UPA Smt. Sonia Gandhi - 27th Jan, 2009
• Completion of Factory Boundary Wall - Dec, 2010
• Completion of Rail Connectivity - Jan, 2011
• Commissioning of 33 KV Transmission line & substation - Jan, 2011
• Roads for Phase I - Started - Oct 2010, Completed - Mar, 2011.
• Finishing Shop - Started - Sept 2010, Completed - Feb, 2011.
• Furnishing Shop - Started - Sept 2010, Completed - Apr, 2011
• Phase-I Production (First coach ready) - 8" April, 2011
• Dedication of the Factory to the Nation - 07 Nov, 2012
• Nos of Coaches out in Year 2011-12 - 18
• Nos of Coaches out in Year 2012-13 - 70