Expenditure till date- 512.81 Cr.
🟢Overall Physical Progress- 50%
🔘Length- 64.30 Km.
🔘Length commissioned- 25.98 Km (Lonand –Phaltan)
🔘Remaining- 38.32 Km (Phaltan – Baramati )
🔘Land acquisition completed- 173.16/237.93 Hectare (72.68%)
A) Completed Sections:25.98 km
🔘Lonand -Phaltan- 25.98 km (40.44%)
B) In Progress Sections- 38.32 km (59.64%)
🔘Phaltan- Malewadi- 9.68 km
🔘Malewadi- Katphal- 28.64 km
🔴Completion of this new line will improve connectivity of this region.
🔘Progress of doubling/3rd/4th lines all over Central Railway’s 5 divisions-
🔘CR has completed 147.77 km multitracking (new line/doubling/3rd/4th line) in current FY from April 2023 till date 2023.
🔘3890 Crs planned by CR in this year for new lines/doubling/3rd/4th line.
🔘2990 Crs expenditure done till date.