#ElectrificationUpdate #26September2019
DAL/DaliGanj Junction - STP/Sitapur Junction electrification update
Poles - 100% (At several stations only cross bars are pending)
Brackets - 62% done (Completion expected by Oct2019)
Wiring - Started on 31-Aug-2019 from...
more... MBP/Mohibullapur. From DAL/DaliGanj Junction wiring started except one patch. Wiring work reached before IT/Itunja (Completion expected by Nov2019)
SSP - Foundation at SD and STP completed (Completion expected by Nov2019)
OHE wire energized - Expected by end of Nov2019
Trial run - Executing company, Kalpataru (
click here is planning to conduct trial run with GD WAP4 on 12-Dec-2019 (Depending on work progress).
CRS inspection - Expected by Dec2019
Commercial uses - Any point of time after successful CRS planned in Jan2020
** All provided dates are tentative.