GTL -HPT Double Electrification FY End Update:
1. RE CRS for GTL(Excl) - BAY(excl) completed last month up to 212.0km at SWR/SCR zones limits .
2. Today CRS Inspection conducted for RE Btn BAY (Incl)- TNGL (Excl) 212.0km-177.6kms but Without E loco
3.BAY: 4 Lines wirings completed still 4 good section s wiring not done ..mainly PF1, 2,3 & one...
more... main goods main still PF1A & goods section left.
4.BYC2 : wiring done only for 2 main lines still 3 siding lines wiring not yet started.
5.wiring completed at KDN & Daroji for all lines ..except BTPS line RE not done.
6. At TNGL wiring done for 7 lines including all 3 pfs but except one main goods line.
7.poles can be seen upto Gadiganuru station .
8. only OHE holes foundation can seen btn Gadiganuru -HPT
Note : Whole GTL -HPT likely to complete in or before December 2019.
photos details
1.Poles till 167.7kms Gadiganuru station
2.No wiring after HPT-BAY NH ROB 175.0kms
3.wiring till TNGL ROB 175.0km
4&5 first time i saw TNGL without Goods trains ..wiring done for 7 lines except one main goods line.
6. CRS inspection done till 177.6kms TNGL outer
7. RE at Daroji
8,9&10.RE at BYC2 only 2 main RE done still 3 lines wiring not done.
11.at BAY
All pics captured by myself