I travelled between Nimbal to Gadag so as we know lachyan michinal doubled but I saw their was line work going on which is on PF-1 of Nimbal and Minchinal Bijapur track laying going in good pace just few km left to reach Bijapur and on other side From Ibrahimpur towards jumnal track laying works going on.. All earth works are almost finished between Ibrahimpur to Wandal but bridge works of krishna, holealur and Gadag jn outer are going on.. And still they need to start parvati katti, and some bridges between Mugalolli Bagalkot.
And also lot of space is created near Bagalkot station so I think Bagalkot yard area will be increased with some two or 3 tracks..