After speed test trial which has happen yesterday 20-Sep-2018 CRS has cleared MKG/ManakNager - ASH/Aishbagh - LC/Lucknow City - DAL/Daliganj section fit for commencement with max speed of 30Km/hr which will be increased later.
For more refer : /news/post/359414
This news is milestone for ASH/Aishbagh - STP/Sitapur GC which was started on 16-May-2016 now its expected that in Oct;2018 mega block of approx 10 days would be taken for diamond like crossing at STP/SCC so that post completion of mega block trial train's (Mostly freight) can run from DAL/Daliganj to STP/Sitapur. If...
more... all goes well then in month of Nov;2018 CRS is expected and by Dec;2018 route would be thrown open for public use.