Dundi to Niwar complete
Niwar station is almost 10-20% incomplete
Niwar to KTES - poles clippers wiring is done
Only final 10% work remains
And KMZ-KTES, KTES-NKJ line is under development.
According...
more... to me it takes 5-7 days to complete the work.