HOSAPETE -GUNTAKAL double electrification update PART 2 from KAR/A,P border to GTL.
1.A.p begins pic 1 u can see erected poles from virapur -sakibanda=5kms electrification 50% completed .
2. sakibanda -bevinahal-sankara=7km single line cable( wire )are being carried poles pic2 electrification 85% completed .
3.sankara-bantanahal-guntakal west=11kms..95% of electrification almost completed pics 3 &4.
4....
more... pic 5 near bantahalu
5 .pic 6 near guntakal west
6.pic 7 men at work fixing wire to pole
7. pic 8 &9 looks like copper wired carried separate coach train.
8. no work in progess near guntakal west for about 3km
9. pic 10 foundation for poles after 2km from guntakal west.
10 . pic 11 near gtl by pass out side -gtl =3.5km erected poles are fixed .
End of it.
my prediction : by dec 2018 SCR can easily complete electrification upto kar/a.p border ..
note :shortly i'll upload full video after editing .