ASH/Aishbagh - STP/Sitapur gauge conversion update :
1. Newly converted track at DAL/DaliGanj Junction has been linked with existing line of ASH/Aishbagh - ML/Malhaur on 29-Apr-2018 (Thanks to Ratansharga ji for news)
2. Non-interlocking at all stations is on going and its expected to get completed by May;2018
3. Mega block at STP/Sitapur WOULD be taken in month of Jun;2018 due technical issue (Route...
more... Relay interlocking system need to be established)
4. Post mega block completion trial will be till STP/Sitapur with empty as well as loaded freight train
5. CRS is expected in month of Jul;2018
6. Post successful CRS trains commencement is expected in month of Aug or Sep;2018 or so
7. Initially 5 set of DEMU would run from ASH/Aishbagh to STP/Sitapur