What ! Panto-graph touching Contact wire in KEQ?
PPI – JBP Electrification Update: -
Electrification Work Progress – KEQ
1. Some track maintenance work in progress between BRGT- KEQ.
2. Workers working “ON TRACKS”. [Pic. 3 &...
more... 4]
3. Track Maintenance Machine Working on Tracks. [Pic 5 & 6]
4. Trains running at a very slow speed under caution order. [Pic 26 to 35]
But “The Legend” not in KEQ or still in SRID
And the reason: -
[08:30 AM KEQ]
Electrification Car with El. team came this morning to KEQ & after opening the pantograph manually electrification car started rolling towards BRGT. During the time experts checking the wire charging status & also measuring the contact wire & Pantograph distance, then OHE Inspection Car Came & went towards MML. After all this “ET Queen” came rolling slowly towards MML under caution order.
Conclusion – Some Patchwork still on near KEQ. Wires still not powered yet & Electrification work delayed due to some track maintenance work near KEQ.
and that’s why DRM Inspection & CRS will be delayed.